How to Use the Mortar Calculator
Start with the volume of finished mortar you need — the wet material that actually ends up in the joints. The easiest source is the brick & block calculator: enter your wall, take its mortar row, and type that figure here. Working by hand, the joint volume approach gives the same answer: joint cross-section (roughly unit depth × joint thickness, allowing for perpends) times total joint length. Typical trade figures land near 0.026 m³ of mortar per m² of metric brickwork and 0.012 m³ per m² of blockwork at a 10 mm joint.
The ratio is cement to sand by volume. Typical practice — and it does vary by country, tradition and the units being laid — runs roughly like this: 1:3 for very strong, exposed work and below damp-proof course in some traditions; 1:4 for general-purpose strong work; 1:5 for everyday bricklaying; 1:6 for internal lightweight blockwork, where a strong mix is harder than the block itself and cracks across the joints. Modern practice replaces the lime that older mixes used with a liquid plasticiser at around a capful per batch, which makes 1:5 and 1:6 mixes workable without lime. Block manufacturers publish recommended mortars for their products — follow those where they exist.
Why the arithmetic is not just "volume divided by parts": dry ingredients and finished mortar occupy different volumes. When you mix cement and sand with water, the cement paste fills the voids between sand grains, and the finished mortar comes out at roughly three-quarters of the dry ingredients' bulk. So one cubic metre of finished mortar needs about 1.33 m³ of dry ingredients — a standard trade factor, and the source of the constant in the formula below. The waste factor then covers what stays in the mixer, the bucket and the wheelbarrow; 10% is a typical default.
Mass follows from two standard constants: cement at 1440 kg/m³ and sand at 1600 kg/m³, both loose bulk densities the trade uses for ordering. One cubic metre of mortar at 1:4 therefore works out to about 383 kg of cement — call it 16 bags of 25 kg — and about 0.44 m³ of sand. A richer 1:3 mix takes about 479 kg (roughly 20 bags) and a leaner 1:6 about 274 kg (11 bags); the sand share moves the other way. Your actual cement may come in 94 lb (42.6 kg) sacks if you are in the US — divide the kilogram figure accordingly.
Two honest limits. First, this is a cement-and-sand tool: lime mortars for older buildings are a different material, gauged on putty or hydraulic lime, and the supplier's guidance beats any generic calculator. Second, mortar is not concrete — it has no coarse aggregate, and using it as one is a false saving. For slabs and footings, see the mortar mix ratios guide for the full background, or the concrete mix ratios guide for the structural stuff.