Build a Patio or Driveway
From setting out the fall to brushing in the joints — the full sequence, the quantities at each stage, and the guides behind the numbers.
A patio or driveway is a sandwich, and the filling matters more than the bread. The surface you see — pavers, slabs or poured concrete — is only the top 50–60 mm (2–2.4 in). Everything beneath it, from the compacted sub-base to the bedding layer to the edge restraint, is what stops the surface settling, rutting and puddling a few years later. Get the base right and almost any surface lasts; get it wrong and nothing does.
This hub puts the whole job in one sequence: plan the area and its fall, excavate to the right depth, total the sub-base in tonnes and the bedding sand in cubic metres, then count pavers with waste and finish the joints. Driveways follow the same steps with heavier numbers — typically more sub-base depth, and a surface rated for vehicle loads rather than foot traffic. If you'd rather pour a slab than lay units, the concrete calculator covers that route too.
The typical figures here — fall rates, bedding depth, sub-base thickness — are common trade practice, not universal rules. Ground conditions and local standards vary, so treat them as starting points and adjust to what the spade tells you.
The Plan
- Set out the area and the fall. Fix the size and shape with string lines and check it against the house, boundaries and doors. Water has to go somewhere: a typical fall is 1–2% (a 10–20 mm drop per metre) away from the building toward a drain or a garden edge.
- Excavate. Dig to the finished level minus the whole build-up — surface, bedding and sub-base — typically around 200–300 mm (8–12 in) down for a patio, more for a driveway. Keep the bottom of the dig firm; over-digging loose soil that then gets backfilled is a classic cause of settling.
- Lay and compact the sub-base. Crushed stone, compacted in layers. A typical compacted thickness is 100 mm (4 in) under patios and 150 mm (6 in) or more under driveways, but it varies with soil and load — the gravel guide covers the reasoning.
- Spread the bedding layer. Sharp sand screeded to a typical 25–40 mm (1–1.6 in) for pavers; concrete slabs are more often laid on a full mortar bed. The paver calculator adds compaction allowance to the sand volume.
- Lay the surface. Pavers in your chosen pattern, slabs on mortar, or a poured slab with its thickness chosen by use. Cuts fall at edges and obstacles — straight patterns typically waste 10%, diagonals and herringbone more.
- Fill the joints. Kiln-dried sand brushed into paver joints and compacted in; mortar joints for slabs. Jointing is what locks a flexible pavement together — skip it and edges creep.
- Edge and finish. An edge restraint stops the surface spreading under load; beds and borders around the paving get mulched, which is where the mulch calculator earns its place on a paving page.
Calculators for This Project
- Paver Calculator Piece counts per m², joint gaps, waste allowance and bedding sand volume in one takeoff.
- Gravel & Sub-Base Calculator Volume, tonnes and 850 kg bulk bags for any depth of crushed stone, sand or pea gravel.
- Concrete Slab & Footing Calculator For the poured-slab route: volume in cubic metres, yards and bag counts, by thickness.
- Mulch & Topsoil Bulk Estimator For the beds and borders that frame the paving — bulk volume or bag counts.
Guides Worth Reading
- How Many Pavers Do I Need? Pieces, patterns, base tonnes and sand — the full patio takeoff, worked through.
- Gravel Sub-Base Guide Depth by load, stone type, compaction — why the layer you never see decides the job.
- Concrete Slab Thickness Choosing thickness by use — patios, drives and shed pads — without over-building.
What This Hub Doesn't Cover
This hub plans quantities and sequence — it doesn't do ground engineering. If the site is soft clay, made-up ground or peat, a standard sub-base may not be enough on its own; geotextile membranes and thicker builds exist for exactly those conditions, and a driveway carrying vehicles over poor soil is worth a professional opinion before the digger arrives. Rainwater runoff is regulated in many places, and draining a large new paved area toward a neighbour's plot or the street is restricted in some countries — settle the drainage before you settle the levels. And before any excavation, locate buried services: many regions run a dial-before-you-dig service, and it's always quicker than the alternative.
Frequently Asked Questions
How much fall does a patio need?
A typical fall is 1–2% away from the house — a 10–20 mm drop per metre of run. Below about 1% puddles start; much above 2% and tables and chairs feel the slope. Driveways follow similar rates toward the drainage point.
How deep should I dig for a patio?
Add up the build-up: paver 50–60 mm, bedding sand 25–40 mm and a compacted sub-base typically 100 mm for patios — roughly 200 mm total, and more for a driveway. The gravel sub-base guide walks the full build-up.
How much paver waste should I allow?
10% is typical for straight-laid pavers with a simple edge. Diagonal patterns, herringbone and curved borders push cuts up — allow 15% or more there. The paver calculator applies the allowance you set.