Build a Patio or Driveway

From setting out the fall to brushing in the joints — the full sequence, the quantities at each stage, and the guides behind the numbers.

A patio or driveway is a sandwich, and the filling matters more than the bread. The surface you see — pavers, slabs or poured concrete — is only the top 50–60 mm (2–2.4 in). Everything beneath it, from the compacted sub-base to the bedding layer to the edge restraint, is what stops the surface settling, rutting and puddling a few years later. Get the base right and almost any surface lasts; get it wrong and nothing does.

This hub puts the whole job in one sequence: plan the area and its fall, excavate to the right depth, total the sub-base in tonnes and the bedding sand in cubic metres, then count pavers with waste and finish the joints. Driveways follow the same steps with heavier numbers — typically more sub-base depth, and a surface rated for vehicle loads rather than foot traffic. If you'd rather pour a slab than lay units, the concrete calculator covers that route too.

The typical figures here — fall rates, bedding depth, sub-base thickness — are common trade practice, not universal rules. Ground conditions and local standards vary, so treat them as starting points and adjust to what the spade tells you.

The Plan

  1. Set out the area and the fall. Fix the size and shape with string lines and check it against the house, boundaries and doors. Water has to go somewhere: a typical fall is 1–2% (a 10–20 mm drop per metre) away from the building toward a drain or a garden edge.
  2. Excavate. Dig to the finished level minus the whole build-up — surface, bedding and sub-base — typically around 200–300 mm (8–12 in) down for a patio, more for a driveway. Keep the bottom of the dig firm; over-digging loose soil that then gets backfilled is a classic cause of settling.
  3. Lay and compact the sub-base. Crushed stone, compacted in layers. A typical compacted thickness is 100 mm (4 in) under patios and 150 mm (6 in) or more under driveways, but it varies with soil and load — the gravel guide covers the reasoning.
  4. Spread the bedding layer. Sharp sand screeded to a typical 25–40 mm (1–1.6 in) for pavers; concrete slabs are more often laid on a full mortar bed. The paver calculator adds compaction allowance to the sand volume.
  5. Lay the surface. Pavers in your chosen pattern, slabs on mortar, or a poured slab with its thickness chosen by use. Cuts fall at edges and obstacles — straight patterns typically waste 10%, diagonals and herringbone more.
  6. Fill the joints. Kiln-dried sand brushed into paver joints and compacted in; mortar joints for slabs. Jointing is what locks a flexible pavement together — skip it and edges creep.
  7. Edge and finish. An edge restraint stops the surface spreading under load; beds and borders around the paving get mulched, which is where the mulch calculator earns its place on a paving page.

Calculators for This Project

Guides Worth Reading

What This Hub Doesn't Cover

This hub plans quantities and sequence — it doesn't do ground engineering. If the site is soft clay, made-up ground or peat, a standard sub-base may not be enough on its own; geotextile membranes and thicker builds exist for exactly those conditions, and a driveway carrying vehicles over poor soil is worth a professional opinion before the digger arrives. Rainwater runoff is regulated in many places, and draining a large new paved area toward a neighbour's plot or the street is restricted in some countries — settle the drainage before you settle the levels. And before any excavation, locate buried services: many regions run a dial-before-you-dig service, and it's always quicker than the alternative.

Frequently Asked Questions

How much fall does a patio need?

A typical fall is 1–2% away from the house — a 10–20 mm drop per metre of run. Below about 1% puddles start; much above 2% and tables and chairs feel the slope. Driveways follow similar rates toward the drainage point.

How deep should I dig for a patio?

Add up the build-up: paver 50–60 mm, bedding sand 25–40 mm and a compacted sub-base typically 100 mm for patios — roughly 200 mm total, and more for a driveway. The gravel sub-base guide walks the full build-up.

How much paver waste should I allow?

10% is typical for straight-laid pavers with a simple edge. Diagonal patterns, herringbone and curved borders push cuts up — allow 15% or more there. The paver calculator applies the allowance you set.